Chip industry update, Q3 2026 Power semiconductors go on allocation as memory price growth slows

From Luke James 7 min Reading Time

AI hardware is drawing capacity away from 200mm power lines, conventional DRAM, and consumer-grade capacitors, while China's gallium export suspension runs out on November 27. AI infrastructure demand pulled silicon power semiconductors into shortage in the third quarter of 2026, joining the memory and passive components that tightened in the first half.

AI infrastructure demand is tightening supply across power semiconductors, memory and passive components, while DRAM price increases are slowing and uncertainty remains over China’s gallium export controls.(Source: ©  IM Imagery - stock.adobe.com)
AI infrastructure demand is tightening supply across power semiconductors, memory and passive components, while DRAM price increases are slowing and uncertainty remains over China’s gallium export controls.
(Source: © IM Imagery - stock.adobe.com)

STMicroelectronics told investors on October 29 that "demand remains well above supply," onsemi lead times passed 50 weeks, with top customers receiving around 70% of the MOSFET and discrete volume they ordered, according to distributor Fusion Worldwide, and Infineon booked €1.7 billion of AI data center power revenue in its fiscal year to September, €200 million more than it had targeted.

Across the component market, suppliers moved capacity toward AI hardware during the quarter, and the products left behind ran short: automotive power parts at onsemi, conventional DRAM as HBM takes more wafers, and consumer MLCCs as capacitor makers prioritize server grades. DRAM contract price increases slowed to an estimated 13-18% in Q3 from 58-63% in Q2, according to TrendForce, as long-term agreements cap server pricing and PC demand contracts. China's suspension of its gallium, germanium, and antimony export ban to the U.S. expires on November 27, and MOFCOM hadn't published an extension as of November 18.

Power demand outruns 200mm capacity

Infineon estimates that each kilowatt of installed AI compute carries $100-250 of power semiconductor content, spread across the power supply units, intermediate bus converters, and voltage regulators that step rack power down to the sub-1 V rails a GPU runs on. Infineon's own data center revenue reached about €2.2 billion in fiscal 2026, and it expects close to €4 billion in fiscal 2027, lifting data center from 13% to around 20% of a business guided to about €20 billion.

The rest of the sector is reporting the same pull. Texas Instruments' data center revenue rose about 95% year on year to 13% of its $6.06 billion Q3 total, and onsemi's rose 175% to $180 million, with CEO Hassane El-Khoury saying in the results statement that rising power requirements "are driving accelerated demand in our AI data center and industrial end markets." Industrial demand is recovering at the same time, with ST's industrial revenue up 40%.

Most power discretes and power management ICs are still built on 200mm wafers, a base that has been shrinking as TSMC and Samsung cut 8-inch capacity to fund advanced nodes and packaging. TSMC's 8-inch Fab 5 is expected to stop production around the end of 2027, according to Taiwanese media cited by TrendForce. TrendForce, meanwhile, puts average 8-inch utilization at the top ten foundries at 88% for 2026, up from 75-80% in 2025. 8-inch foundry prices rose 5-15% between Q1 and Q2, and a third round is in preparation.

onsemi's automotive revenue fell 1% to $777 million in the quarter, while its AI data center revenue nearly tripled, and management described a short-term shift in supply allocation away from automotive inventory replenishment. Fusion Worldwide's October Greensheet put onsemi lead times above 50 weeks, up from 26 weeks or more in January. Power buyers are now securing supply the way cloud providers did with memory, and Infineon said on its November 10 call that multi-year supply agreements signed or under negotiation exceed €10 billion.

At ST, book-to-bill was "well above 2 overall," CEO Jean-Marc Chery told analysts, with distribution inventory still below target. Its Power & Discrete segment grew 11.3% to $477 million but posted an operating loss of $81 million, narrower than Q2's $99 million, which management attributed to the transition to 200mm wafers and legacy fab costs.

Silicon carbide, which sits in the same ST segment, is still oversupplied. Chinese capacity drove 6-inch SiC substrate prices below $500 a wafer in 2025, and Digitimes reported in October that they were bottoming out, but device makers are still losing money. Wolfspeed reported a -22% GAAP gross margin on $155.0 million of revenue for the quarter ended September 27, roughly level with May, and SK Siltron has begun liquidating its U.S. SiC wafer subsidiary. Rohm raised its full-year forecast after SiC device and module sales grew 41% in its first half, but TECHi calculates that about 85% of its profit gain came from lower depreciation after the ¥163.2 billion SiC impairment it booked for the fiscal year that ended in March.

Subscribe to the newsletter now

Don't Miss out on Our Best Content

By clicking on „Subscribe to Newsletter“ I agree to the processing and use of my data according to the consent form (please expand for details) and accept the Terms of Use. For more information, please see our Privacy Policy.

Unfold for details of your consent

Memory price growth slows, supply doesn't loosen

TrendForce forecasts conventional DRAM contract prices to rise another 10-15% in Q4, a fraction of the 93-98% and 58-63% increases in the first half. Compounding its quarterly midpoints still leaves contract prices at roughly four times their end-2025 level by year-end. The U.S. cloud providers that buy the most server DRAM have signed multi-year agreements that restrict how far suppliers can raise their prices, TrendForce reported in July. PC demand, meanwhile, is contracting under the increases already passed on: notebook shipments fell 14% quarter on quarter in Q3, TrendForce forecasts a further 9% drop in Q4, and OEM DRAM inventory rose from six to nine weeks to seven to ten.

HBM continues to take wafers from conventional DRAM. TrendForce expects HBM's share of DRAM wafer starts to rise from 22% at the end of 2026 to 30% a year later, and warns that PC DRAM supply could fall in 2027 as manufacturers prioritize server products. SK hynix said HBM4 will overtake HBM3E in volume and revenue this quarter and that long-term agreements with 14 customers cover more than half of its 2027-2028 capacity. Micron said most of its calendar 2027 HBM supply is already contracted, and CEO Sanjay Mehrotra expects conditions to be "much tighter in fiscal 2027 and 2028" than this year.

TrendForce's November 18 forecast has quarterly increases narrowing from 5-10% in Q1 2027 to 0-5% by the second half, according to reports from its Seoul roadshow. Device makers are already cutting product lines: Oppo has pulled OnePlus out of North America and Europe and Realme out of China, with the memory shortage a key factor, according to TechInsights.

Passives and grid hardware

A single Nvidia GB200 NVL72 rack contains roughly 440,000 MLCCs, and Samsung Electro-Mechanics, Murata, and Yageo had no inventory of certain high-capacitance server parts by mid-August, according to Korean securities reports cited by TrendForce. High-end MLCC lead times reached five to ten months, up from 20-26 weeks in Q2. As capacitor makers move production toward AI-grade parts, the shortage is spreading to consumer products. TrendForce estimates Samsung Electro-Mechanics' Q4 increases to OEM and ODM customers at 10-20% for AI-server X6S parts but 25-30% for consumer X5R, which the Korea Herald attributed to that shift in production. The company hasn't confirmed the figures.

The same power demand is stretching equipment outside the data center. Generator step-up transformer lead times exceeded 160 weeks in Q1 2026, up from 143 weeks in 2024, Wood Mackenzie senior analyst Ben Boucher told Reuters in July, while the firm projects U.S. data center capacity growing from about 24 GW to 110 GW by 2030. Copper for transformer windings, busbars, and cabling set records in September amid U.S. tariff uncertainty, with LME three-month copper reaching $14,533 per metric ton and COMEX $6.9285 per pound. LME cash copper had eased to $13,225.50 by November 17.

Nexperia's split heads to appeal

Buyers moved discrete orders away from Nexperia after its Chinese and Dutch operations split last October, and Fusion Worldwide said in March that Infineon's lead times had doubled to 30-52 weeks as it absorbed the overflow. The Amsterdam Enterprise Chamber ruled on November 11 that Nexperia's court-appointed officials may explore long-term solutions for the company, and ordered Wingtech and Nexperia China not to interfere. Wingtech said it will appeal and that penalties could reach €300 million, Caixin reported, and Nexperia entities have separately sued Wingtech in Amsterdam for $2 billion.

Wingtech rejected a proposal on November 4 that would let it keep Nexperia China while outside investors took control of the rest of the business. The officials have said they are "not currently preparing a sale of a majority stake," according to Bits&Chips, while the South China Morning Post reported that they would sound out investors on a majority or minority holding. Whatever structure the courts settle on, buyers are already dealing with two suppliers: the Dongguan unit building a supply chain on domestic wafers, and a rest-of-world business requalifying assembly outside China.

The November deadline arrives

MOFCOM Announcement No. 72 suspended China's ban on gallium, germanium, antimony, and superhard material exports to the U.S. until November 27. If it lapses, the December 2024 ban returns for U.S. buyers. An extension wouldn't remove Beijing's control either, since the licensing requirement in place since August 2023 and the ban on sales to U.S. military end-users were never suspended. China produces around 94% of the world's gallium, according to a 2024 EU report, and gallium is the base material for the GaN power devices that TechInsights expects to gain ground in data center power systems.

The wider truce runs to January 10, 2027, and Presidents Trump and Xi are due to meet in Shenzhen on November 19. It rests on an unwritten bargain in which Washington holds off on new tech curbs, and Beijing keeps critical minerals flowing, The Next Web reported. Days before the meeting, the U.S. Commerce Department added license requirements for advanced AI chips bound for data centers in Singapore, Malaysia, Thailand, Indonesia, and Brazil, CNN reported.

Looking ahead

Our 2026 outlook expected power semiconductor capacity to run well below full utilization until 2027-2028. For 200mm silicon, 88% foundry utilization means that slack is gone, and TrendForce expects global 8-inch capacity to keep shrinking through the first half of 2027 while PSMC plans 10-20% foundry price increases next year. SiC remains the exception, with Wolfspeed guiding non-GAAP gross margin only to approach breakeven this quarter.

In memory, TrendForce's forecast slows the rate of increase without returning wafers to conventional DRAM, as HBM's share of wafer starts climbs toward 30%. On materials, MOFCOM has eight days after the Shenzhen meeting to extend the gallium, germanium, and antimony suspension, and the truce behind it expires 44 days later.